Check list for examination of Procurement (Works/ Purchases/ Services) Contracts
- Pre-Award Stage
- Financial and Technical sanction of competent authority is available.
- Adequate and wide publicity is given. Advertisement is posted on website and tender documents are available for downloading.
- Convenient tender receiving/opening time and address of the tender receiving officials/tender box are properly notified.
- In the case of limited tender, panel is prepared in a transparent manner clearly publishing the eligibility criteria. The panel is updated regularly.
- Pre-qualification criteria are properly defined/ notified.
- Short listed firms/consultants are fulfilling the eligibility criteria. There is no deviation from notified criteria during evaluation.
- Experience certificates submitted have been duly verified.
- Tenders/bids are opened in the presence of bidders.
- Corrections/omissions/additions etc., in price bid are properly numbered and attested and accounted page wise. Tender summary note/ Tender opening register is scrupulously maintained.
- Conditions having financial implications are not altered after opening of the price bids.
- In case of consultancy contracts (a)Upper ceiling limit is fixed for consultancy fee and (b) Separate rates for repetitive works are fixed.
- Post-award stage
- General
- Agreement is complete with all relevant papers such as pre-bid conference minutes, etc.
- Agreement is page-numbered, signed and sealed properly.
- Bank Guarantee is verified from issuing bank.
- Insurance policies, labour licence, performance guarantee are taken as per contract.
- Technical personnel are deployed as per contract.
- Plant and equipment are deployed as per contract.
- Action for levy of liquidated damages is taken in case of delay/default.
- Payments to contractors
- Price escalation is paid only as per contract.
- Retention Money/Security Deposit is deducted as per contract.
- Recovery of Mobilisation & Equipment advance is made as per the provisions in the contract.
- Recovery of I.Tax & Works Contract tax is made as per provisions in the contract.
- Glaring deviations are supported with adequate justification and are not advantageous to the contractor.
- Site Records
- Proper system of recording and compliance of the instructions issued to the contractors is maintained.
- Proper record of hindrances is maintained for the purpose of timely removal of the hindrance and action for levy of liquidated damages.
- Mandatory tests are carried out as per the frequency prescribed in the Agreement.
For complaints against corruption please dial Toll free number: 1800 345 3984